Sunville rail were awarded the contract to pull and install 2 x New 5 core cables 375M long at Morden.
Following a report on the existing LV cable supplying power between the REC Switch room & North Wash Plantroom at Morden train depot.
Sunville rail were awarded the contract to pull and install 2 x New 5 core cables 375M long at Morden.
Sunville rail carried out the following works:
· Survey, design and planning
· vegetation clearance along cable route
· Break out existing concrete to form trench
· Reinstate concrete to new trench
· Pull and install 375M of LV cables and feed through buried duct and URX section
· Remove excess waste from site