Project Specifications

  • ClientOctavius
  • LocationLiss Station
  • SNV Rail DisciplineHv Feeder Route, Ex-Vac, Safe excavation, Waterworks, Tarmac, Buried Route
  • Project Duration3 Months

About Project

Sunville Rail were awarded the contract by our client Octavius Infrastructure as part of the SID020 HV Feeder Renewals Package 2 Liss Station carrying out HV buried route installation, Buried water pipe route installation & associated works

Project Overview

ABOUT THE PROJECT  

Sunville Rail were awarded the contract by our client Octavius Infrastructure as part of the SID020 HV Feeder Renewals Package 2 Liss Station carrying out HV buried route installation, Buried water pipe route installation & associated work  

PROJECT OVERVIEW  

Sunville Rail were required to supply the necessary labour, plant, equipment and materials to undertake the construction of 6 way duct route through Liss business park adjacent to the train station, Sunville Rail also installed a new waterpipe to feed water route to the businesses with the business park.  

Sunville Rail were responsible for completing the below works; 

• Provide all provision of labour

• Organise all aggregate and material deliveries to site

• Install 6way Cubis ducting or flexi duct routes.

• Supply suction excavator operative and associated banksmen.

• Carry out machine and hand excavation throughout

• Concrete, type I and tarmac reinstatement

• Removal and disposal of inert waste

• Provide planned look ahead and hour by hour reporting of works

• Concrete troughing install

• Install new buried waterpipe route

• Reinstate road tarmac